Join the project manager Jaap Hogendorp for a day

What a lovely day today! The sun shone nicely today at high voltage substation IJsselmuiden. Today I had a great time working on one of my favorite projects! The expansion and reinforcement at IJsselmuiden. The day-to-day business on site is also run by an experienced Construction Manager.

In the photo you can see the construction of the new 90MVA SGB transformer. Always nice to see. The SAT is next week and the transformer change is planned for December 1st. Here, too, I achieved maximum transformer load with an enthusiastic project team. This new transformer will be operational at the end of this year and the new solar and wind farms in the Kampen/IJsselmuiden area can be connected from next year. Here too, the Energy Transition is one step further and this station is future-proof.